Welcome to the complete guide on how to correctly fill a Lifting Plan as an Appointed Person (AP). This detailed guide is designed for candidates and professionals who are preparing lift plans, based on industry best practices.
Use this guide step-by-step to understand and fill each field of the lifting plan accurately.
1. General Information
Date of Lifting Operation
What to Fill:
- The actual date when the lift will happen.
Example:
- 22nd August 2025
Pro Tip: Always write planned date; if delayed, update.
Site Address
What to Fill:
- Complete address where the lift will occur.
Example:
- Smart Vision Yard, Industrial Area, Muscat, Oman
Prepared By (Appointed Person)
What to Fill:
- Name of the person who prepared the plan.
Example:
- Alex Crane
Lift Operation Reference Number
What to Fill:
- Unique number for tracking the lift.
Example:
- 001
Pro Tip: Use simple numbering (001, 002, etc.)
Lifting Supervisor
What to Fill:
- Name of person supervising the lift.
Example:
- Michael Strong
Location of Lift
What to Fill:
- Specific area of lift (not general site).
Example:
- Storage Yard, Smart Vision Industrial Area
2. General Details
Customer
What to Fill:
- Who requested the lift.
Example:
- Smart Vision Gulf
Site Contact and Contact Number
What to Fill:
- Name and phone of site responsible person.
Example:
- Sarah Ali, +968 91234567
Description of Lift
What to Fill:
- What exactly you are lifting and moving.
Example:
- Lift bundle of steel pipes from truck and place behind a security wall on wooden bearers.
General Ground Conditions
What to Fill:
- Type of ground at lifting area (soft, hard, drains, slopes).
Example:
- Asphalt surface at entrance, soft ground in operational area, presence of underground utilities.
3. Lifting Plan Diagram
What to Do:
Draw the lift site area.
Show crane location, vehicle location, hazards (cables, drains, walls).
Pro Tip:
Use arrows to show movement from pickup to deposit area.
Mark entrance, fences, overhead hazards.

4. Details of the Load
Load Description
What to Fill:
- Type of load.
Example:
- 6 x Mild Steel Tubes
Load Dimensions
What to Fill:
- Size of load: length, diameter, wall thickness.
Example:
- Length: 5m, Diameter: 0.30m, Wall Thickness: 10mm
Position of Centre of Gravity (COG)
What to Fill:
- Where load balances (normally center if uniform).
Example:
- Centre
Height of Lift
How to Calculate:
- From ground/truck to final landing height.
Example Calculation:
- Truck bed 1.4m + Wall 5m ≈ Lift height 6m
Maximum Radius
How to Estimate:
- Measure from crane center to load pickup.
Example:
- 8m
5. Details of the Crane
Type of Crane
What to Fill:
- Type used (mobile, crawler, tower, etc.)
Example:
- Mobile Crane
Make and Model
What to Fill:
- Manufacturer and model number.
Example:
- Zoomlion QY-30V
Rated Capacity
What to Fill:
- Crane’s lifting capacity at given radius.
Example:
- SWL ~16T @ 8m Radius
Boom Length, Outrigger Spread, Stabiliser Pads
What to Fill:
- Values from crane specification.
Example:
- Boom: 32m max height, Outrigger Spread: Standard for Zoomlion QY-30V
Rigged Weight
What to Fill:
- Weight of fully rigged crane.
Example:
- Approximately 28T
6. Lifting Accessories
List slings, shackles, spreaders, and their SWL (Safe Working Load).
Example:
1x Spreader Beam SWL 10T
2x Webbing Slings SWL 3T each
1x Chain Sling 4-Leg SWL 6.75T
Slinging Method:
- How accessories are used to connect to load.
7. Proximity Hazard Identification
Fill ‘Yes’ or ‘No’ and describe:
Overhead cables?
Underground services?
Confined area?
Pedestrian/forklift movement?
Example:
Overhead Cables – YES – Near entrance
Soft ground – YES – Around forklift path
8. Load Hazard Identification
Check:
Slinging difficulty?
Sharp edges?
Load top-heavy?
Example:
- Slinging difficulty: YES – Place bearers under load.
9. Risk Assessment
List potential risks and control measures.
Example:
Crane Movement ➔ Barrier off lifting area, banksman guide.
Bad Weather ➔ Use anemometer, suspend lift if wind exceeds limit.
10. General Operational Requirements
Checklist:
PPE (Helmet, vest, gloves)
Barriers and warning signs
Induction and briefing for all personnel
11. Sequence of Operations
List the order of activities:
Site inspection
Crane setup
Lifting accessories inspection
Pre-lift dummy test
Actual lift
Load placement
Crane derigging
12. Contingency Plans
If any unexpected events:
Stop the lift.
Inform Appointed Person.
Secure the site.
Examples:
Unauthorized person enters site.
High winds or thunderstorms.
Crane breakdown.
13. Personnel Details
List names and roles:
Lifting Supervisor
Crane Operator
Slinger/Signaller
Appointed Person
Each must sign acknowledging understanding of the lift plan.
✨ Conclusion
By carefully reading and understanding each section, you can create a safe, professional, and compliant lifting plan.
Remember: A well-prepared lift plan is not just paperwork; it is the foundation of a safe lifting operation.
📢 EngineerHow.com Promotion
At the bottom of your article, you should always add this:
Posted by EngineerHow.com — Empowering Engineers and Safety Professionals with Knowledge.
🔔 For more guides, templates, and training support, visit EngineerHow.com and explore our resources.
📺 Subscribe to our YouTube Channel for video tutorials, live examples, and expert discussions!
📝 Feel free to comment below, share this article, and let us know what topics you would like to see next!